18. If more than 200 metric tonnes of contaminated soils are to be transported, the receiving site manager must, before the soils may leave their site of origin, and in addition to the manager’s other requirements under the preceding provisions, provide the Minister with confirmation that the manager has agreed with the signatory of the tracking slip for the soils under section 14 that the soils may be discharged at the receiving site.
O.C. 877-2021, s. 18.
In force: 2021-11-01
18. If more than 200 metric tonnes of contaminated soils are to be transported, the receiving site manager must, before the soils may leave their site of origin, and in addition to the manager’s other requirements under the preceding provisions, provide the Minister with confirmation that the manager has agreed with the signatory of the tracking slip for the soils under section 14 that the soils may be discharged at the receiving site.